Green Technologies Solutions AS · RSV-PDG-SLD-001-C · 1050 VDC distribution

RSV Power Flow Simulator

Load-flow model of the three DC switchboard sections (SARG-A / B / C), five 1512 ekW gensets, two 2508 kWh / 3200 kW energy storage strings and all drive feeders. Worst-case failure is the loss of a complete outer section; the default scenario runs the surviving thrusters at 75%, the crane at 50% and allows the surviving battery to boost the grid.

Total demand
5,586kW
7 feeders energised
Diesel generation
4,536kW
3 × gensets · 100% engine load
Battery boost
1,050kW
3,200 kW available · 1,756 kWh usable
Reserve margin
2,150kW
Generation + ESS above demand
Battery endurance
100min
Until reserve SOC is reached

Scenario

Failed switchboard section
Thruster load75 %
Crane load50 %

Crane (2100 kW) is fed from SARG-A. If SARG-A is the lost section the crane is unavailable regardless of setting.

480 V distribution
Distr. Trans No.1 → PS board450 kW
Distr. Trans No.3 → STB board450 kW

Base board load excluding the ROVs. Each transformer is 1500 kVA; ROV load is added on top of the value set here.

The 480 V / 208 V bus-ties are normally open. On loss of SARG-A or SARG-C the motorized breaker between the distribution transformer and its 480 V board opens, so the dead board cannot be back-fed even with the tie closed manually — ROVs must be transferred to the surviving board.

ROV load300 kW
ROV load300 kW
Deck utility / aux transformers150 kW
Battery state of charge90 %
Reserved SOC (not dischargeable)20 %
Additional genset unavailable (N-2)
Drive / converter efficiency96 %

Live single-line balance

Fault: SARG-C lost
SARG-A · DC MSB PS · 1050 VDC / 5500 A
G1
1,512 / 1,512 kW
G2
1,512 / 1,512 kW
ESS
1,050 / 3,200 kW
MP1
1,445 / 1,850 kW
RBT2
1,055 / 1,350 kW
CRANE
1,094 / 2,100 kW
TR1
781 / 1,500 kW
DK1
132 / 400 kW
ROV1
0 / 500 kW
Bus throughput4,507 kW · 78% of 5,775 kW
Net import433 kW
2 × DCGuard
433 kW
6%
SARG-B · DC MSB CENTER · 1050 VDC / 4000 A
G3
1,512 / 1,512 kW
BTT1
1,055 / 1,350 kW
AUX2
25 / 75 kW
Bus throughput1,512 kW · 36% of 4,200 kW
Net export433 kW
2 × DCGuard
0 kW
0%
SARG-C · DC MSB STB · 1050 VDC / 5500 A
DE-ENERGISED — section lost
G4
0 / 1,512 kW
G5
0 / 1,512 kW
ESS
0 / 3,200 kW
MP2
0 / 1,850 kW
RBT3
0 / 1,350 kW
TR3
0 / 1,500 kW
DK3
0 / 400 kW
ROV2
0 / 500 kW
Bus throughput0 kW · 0% of 5,775 kW
Net export0 kW

Analysis

SARG-C lost — G4+G5, ESS2, MP2, RBT3 and the STB 480 V board are gone

Losing SARG-C removes 3 024 ekW of generation and one 2 508 kWh battery, but the crane stays available on SARG-A. This is the governing case for the power balance, because the crane load remains on a halved plant.

Diesel plant is at 100% — battery is carrying 1,050 kW

Load exceeds the online gensets by 1,050 kW. The surviving ESS covers it (33% of its 3 200 kW converter). With 1,756 kWh usable this can be sustained for 100 min before the reserve SOC is reached.

Bus-tie transfer 433 kW — 6% of the DCGuard pair

Each tie is 2 × DCGuard 3200 A at 1050 VDC = 6,720 kW. The surviving sections must be able to move power across the ties, so the DCGuards must stay closed after the fault — an FMEA-relevant point, since a spurious tie trip converts this into a second, deeper failure.

Thruster headroom: 53% on diesel only, 100% with ESS boost

Maximum simultaneous thruster loading the surviving plant can sustain with the crane, 480 V board and ROV demand held constant.

Battery endurance 100 min at 1,050 kW

1,756 kWh usable (SOC 90% down to 20% reserve). Beyond this the load must be back inside the diesel envelope, so the operation needs a defined ramp-down or a recovery plan within that window.

ROV2 (assigned to STB) lost with the failed section

The selected 480 V board is de-energised: the motorized breaker between the distribution transformer and its board opens when the feeding SARG section is lost, so the board cannot be back-fed even after the 480 V / 208 V bus-ties are closed manually. The ROV must be transferred to the surviving board — a break-before-make operation.

480 V distribution transformers

TR1 · PS 480 V board50%
750 / 1,500 kVA
450 kW board load + 300 kW ROV
TR3 · STB 480 V board0%
0 / 1,500 kVA
Board de-energised — transformer incomer breaker opened with the section loss; no back-feed via the 480 V tie

Feeder schedule

TagConsumerSecFeederRatedDemandLoad
MP1Main propulsion PS (cycloidal)A1900 kW / 2080 A1,850 kW1,445 kW75%
RBT2Retractable bow thruster PSA1300 kW / 1400 A1,350 kW1,055 kW75%
CRANECrane (dual motor 2 x 1300 A)A1400 kW / 1500 A2,100 kW1,094 kW50%
TR1Distr. Trans No.1 → PS 480 V board(incl. 300 kW ROV)A1552 kVA / 1500 kVA1,500 kW781 kW50%
DK1PS deck utility (690 V, Transf No.6)A359 kVA400 kW132 kW32%
BTT1Bow tunnel thrusterB1350 kW1,350 kW1,055 kW75%
AUX2Aux Transf No.2 (660/480/208 V)B283 kVA75 kW25 kW32%
MP2Main propulsion STB (cycloidal)C2800 kW1,850 kW0 kW0%
RBT3Retractable bow thruster STBC1300 kW / 1400 A1,350 kW0 kW0%
TR3Distr. Trans No.3 → STB 480 V boardC1552 kVA / 1500 kVA1,500 kW0 kW0%
DK3STB deck utility (690 V)C352 kVA400 kW0 kW0%
ROV1ROV1 on PS 480 V board(via 480 V board)A480 V / 630AF-450AT500 kW300 kW60%
ROV2ROV2 on STB 480 V board(board de-energised)C480 V / 630AF-450AT500 kW0 kW0%

Demand is referred to the DC bus and includes drive/transformer losses at the selected efficiency. ROV demand is drawn through the 480 V board it is assigned to, so it appears inside the TR1 / TR3 feeder figure and is not counted twice.